A group called TysonsTunnel.org is fighting to get the Commonwealth, most specifically Governor Kaine and Virginia Secretary of Transportation Pierce Homer, to do two things, neither of which have been done to date:
TysonsTunnel.org is begging for adequate and accurate media coverage. With nearly 15,000 petition signatures to date (sign the online petition), TysonsTunnel.org is not giving up its grassroots effort to get the tunnel considered and to get the entire project bid. This important decision will impact Virginia for 100+ years. To have a $4B contract go to a single source without adequately considering other contractors is ludicrous. I call on Governor Kaine, SecTrans Homer, and our NoVA congressional delegation to make the right choice for Virginia instead of the right choice for the bank accounts of the fat cats of Bechtel.
By the way, Bechtel does not do tunneling the way it would have to be done in Tysons. Bechtel does "tunnels" by way of "cut and cover" - that's how they did the "Big Dig" in Boston. On the other hand, the tunneling technology that TysonsTunnel.org is proposing for Tysons is the same technology that is being used around the world, most notably in the building of the "Chunnel", which I believe came in under budget and ahead of schedule.The hard, quantifiable fact of estimated lower costs and construction time is joined by the following list of advantages a tunnel has:
The Elevated Railway option promises to bring an elevated concrete structure (70 feet high in some locations at Tysons) with piers every 100 feet. Picture the "Mixing Bowl" where I-395 meets I-495 and you get the idea of the enormity and height of this construction project slated for Tysons. Construction vehicles will snarl traffic for an estimated four years! Every INCH of Rte. 7 from Koons Auto Dealership (at Rte. 123) down to the Toll Road would need to be torn up to accommodate the widening of Rte. 7 so that the elevated structure could run down the median.
In contrast, the Tunnel option would take an estimated 8 months shorter construction time, and all construction would take place underground, with the small exception of the station drilling that would take place on four small footprints in the Tysons area. Construction vehicles would be limited to either end of the tunnel, to remove the "muck" (a technical term) from the tunnel boring machine. That tunnel boring machine could work 24 hours per day, 7 days per week, with no delays due to weather or utility relocation (there is no need to relocate utilities since the tunneling takes place BELOW all of the utilities).
I believe that a careful analysis of the Tunnel option - with a delay no greater than an estimated several months (it is estimated that the construction time saved on the Tunnel option would more than make up for this upfront time involved in analyzing the option) - is what is needed given this monumental, 100+ year decision that the Commonwealth (your tax dollars!) is about to fund.
TysonsTunnel.org needs our help - it is being run by the McLean Chamber of Commerce and is operating on donations alone. It is begging for adequate and accurate media coverage. With nearly 15,000 petition signatures to date (sign the online petition), TysonsTunnel.org is not giving up its grassroots effort to get the tunnel considered and to get the entire project bid. To have a $4B contract go to a single source without adequately considering other contractors is ludicrous. We must get our government to make the right choice for Virginia instead of the right choice for the fat cats of Bechtel.
They also mentioned that they had gotten a fixed-cost bid from the Spanish company that had done some of the previous work, and the bid came in 2-300$ million less than their previous estimate. They will have a press release sometime in the next couple of days. I don't know how this new price compares to the overhead approach, but Bechtel is late in delivering their own bid.
I don't know if these are technically bids however, I suppose what they got was a far more detailed cost estimate for the project, and the company is now comfortable enough in the costs that they are willing to make it fixed-cost.
Bechtel spreads a lot of money around in NoVa to get what it wants.
$50,000 to Citizens for Better Transportation. The "Citizen" seems to be developer Myron P. Erkiletian.
Bechtel also gives to Gillmore's New Majority Project that gives to the incumbents.
Bechtel's PAC gave Tom Davis $10k, the last $3 right before he paid a visit to Gov Kaine to tell Kaine to back off the tunnel. Bechtel exec Wiliam Friend and his wife personally gave Davis $15k.
I wonder how Bechtel has made so many millions while it escaped inquiry from the Government Reform Committee while Tom Davis was Chair?
I mean - I am sure he could put pressure but last I checked he is a US congressman not a VA delegate.
1. Sole-source/no-bid contract
2. Elevated railway instead of tunnel
Neither are the right choice for VA and the method used to arrive at the current choice is dubious at best.
I am going to Bible college in PA right now and have little to no time to pursue this vigorously. I am just getting ready to embark on a weeklong choir tour to Canada.
I am counting on y'all to pick up the ball and run with it. We must create a grassroots stir about this matter and force the VA government to at least give the tunnel a fair and public hearing. Let's do what the blogosphere does best.