"We don't know where the FTA is on this project," said Virginia Secretary of Transportation Pierce Homer.Last week Homer called a gathering of Northern Virginia's General Assembly delegation, virtually all of whom signed a letter to the FTA pledging unqualified support for rail in the Dulles Corridor.
"Please take the necessary immediate action to advance rail in the Dulles Corridor," the letter reads.
The letter made no mention of the much-discussed tunnel option, although many of the northern Fairfax representatives had campaigned on their support for the tunnel.
That's right, the FTA appears ready to reject the entire mega-billion-dollar project, one of the largest projects ever undertaken in the Commonwealth, and the Virginia powers-that-be are in a panic. What I'm hearing is that huge amounts of pressure have been applied to recalcitrant (aka, "principled") General Assembly members to change their positions and support the project, as is (e.g., no-bid contract for Bechtel, aerial option in Tysons, questionable economics, lack of capacity on Orange Line to handle the increased traffic, you name it)...or else.
Two officials -- Dranesville Supervisor John Foust (D) and (of all people) Sen. Ken Cuccinelli (R-37) appear to be holding their ground:
"Rather than waste more federal, state and local resources trying to make this dreadful project work, we should kill the project forthwith," Cuccinelli wrote.Dranesville Supervisor John Foust...has urged the FTA to take a "timeout" on the project.
"The best approach would be a timeout, to allow time to give a fair decision to the tunnel without the project going to the end of the line for funding," Foust said.
Foust and Cuccinelli are correct, of course. Unfortunately, others appear to have buckled under the enormous pressure they've reportedly received from higher ups:
"We were told by the secretary that if there were to be a timeout, the project is as good as dead," said Vanderhye.Vanderhye endorsed Homer's initiative despite pressure from the McLean Citizen's Association, urging her to ask for a timeout as well.
State Sen. Chap Petersen (D-Vienna) also sent a letter to the FTA asking for a timeout, but directly contradicted himself a week later by signing Homer's letter asking for the project to be approved before Feb. 1.
"I'm not taking my letter back, I'm trying to walk a fine line," Petersen said Monday, adding that before the meeting with Homer he did not have all the information.
"I don't want to see the whole project disappear. ... I don't want to throw the baby out with the bathwater," Petersen said. "To prevent that, I'll take a little bit of embarrassment."
The sad thing about this project is it never had to get to this point. Unfortunately, wrong decision has followed wrong decision, and now we're faced with a mega-project that will cost a fortune but which makes very little sense for Virginia. Gridlock on the existing Orange Line Metro (I can just imagine rush hour now -- so much for catching a train in Arlingon!), a guarantee that there will NOT be "smart growth" in Tysons, almost certain cost overruns from no-bid, Big Dig Bechtel -- that's what awaits us. Or, the FTA might simply cancel the project, meaning that Virginia is left with no rail interconnection to its major international hub, Dulles Airport. Brilliant.
Anyway, if you want to read the letters, here they are. Enjoy.
Congressional delegation letter
General Assembly letter
Chap Petersen letter
John Foust letter
Kaine, O'Malley, Fenty letter
For the majority of Tysons land owners, a very robust circulator system will be required. Clark Tyler, chairman of the Tysons Task Force has been preaching that the current design will not work without such a system and also believes that such a system must have dedicated right-of-way so it can maintain a regular schedule. Such a system renders heavy rail through Tysons irrelevant.
The current proposal is fatally flawed and should die.
I've said it before, a fifty to one hundred year mass transit design should not be driven by short-sighted real estate interests who control our elected officials.
The congestion question still remains - with the "tubes" near capacity with trains when the Blue and Orange meet at Rosslyn, how the hell will the rail lines support a 50% increase in traffic? As it currently stands, a disabled train or medical emergency can easily back up the morning commute by 15 - 20 minutes. Throw in an additional 50% more trains and it will cause total gridlock.
a) Drive to Franconia Springfield and park, god knows how long that will take
b) Catch the blue line to Rosslyn
c) Attempt to transfer to the Silver Line to Dulles. Watch several packed trains go by.
d) Perhaps 30 minutes later, finally squeeze onto a Silver Line train to Dulles.
e) Reach page 100 of War and Peace.
f) Arrive at airport, find that you've missed your flight and that there won't be another one until tomorrow.
g) Get back on Silver Line heading towards Rosslyn...etc.
"It's very frustrating," said Ken Clendenin, a paralegal who is a regular rider, before backing away from another train packed shoulder to shoulder. "Sometimes I have to let two or three pass. But what are you going to do?"The Orange Line crowding stems from what may be the most significant choke point in the region's Metrorail system: the narrow tunnel beneath the Potomac River. It serves Orange and Blue Line trains shuttling between Northern Virginia and Washington but is wide enough for just one track in each direction.
OK, now, add the Silver Line to this mix and what do you get? I'd like to hear from Arlington officials about this...seems to me that Arlington's getting totally screwed here.
http://www.examiner.com/a-8572...
This might help a bit but it would of course increase blue line traffic on the trains actually going to Rosslyn and Rosslyn tunnel use would still increase by 25% from 4 trains per cycle (2 Orange 2 Blue) to 5 trains per cycle (2 Orange 1 Blue 2 Silver)
But reading their proposal, they are cutting Blue line service in half. I thought they'd be just bypassing a number of blue stops (Arlington cemetery through Smithsonian... cough cough... don't these cover the primary tourist destinations?) and the blue train would pick up and finish off the blue route. But it appears they're just turning every other Blue line train into a Yellow line train (except for the Van Dorn and Springfield stops). I don't think the Blue is as crowded as the Orange is now, but it will be after this change.
Plus, as you say, it's still a 25% increase in tunnel traffic.
By the time the silver lane is running there will be 8 car trains everywhere
Also remember that the new car designs can handle up to 25% more passengers per car so you are talking as much as a 50% increase in throughput going from an old 6 car design to a new 8 car design
Bottom line though I think (I agree with you) that the Silver Line is not a good idea in its current form
I actually know people who get off packed trains in West Falls Church and wait for one of these tripper trains so that they can get a seat and be more comfortable.
And it shouldn't just be the FTA taking a very close look at this ill-conceived deal -- it should be the news media too! They've given Governor Kaine, Pierce Homer, et al
a free ride so far. Those incompetents have royally screwed things up, and have the nerve to point fingers at others. They're trying to push through an agreement that even Gerry Connolly says is bad. The Feds are apparently the only people being responsible now.
And, to top it off, now streets are being torn up in Tysons "at the request of the airports authority by [Bechtel and Washington Group], basically to keep the
contractors busy so the cost penalties were not incurred." The part in quotes is, incredibly, straight from the mouth of Pierce Homer!
If all of this weren't so important and sad, it would be funny.
Maybe it's not too late, though...because there
is a solution: Competitively bid the project, with the option for the tunnel that EVERYONE says is best.
This crap politicians spout about any delay killing the whole project is just that -- crap. I've been hearing that a 6-month delay would kill rail to Dulles more than a year-and-a-half. Negotiations have been going on for years. It is ludicrous to think that another minor delay, to do this the right way, will kill everything.
The media should start to inject a little reason into this...and paint a true portrait about how it's been screwed up so far. The public, weary of all the
back-and-forth on this issue, still doesn't have a clear picture of what's really going on...and how badly they are being served.
There is currently no money allocated for extending service to the airport. At this time, the project is more aptly called "Tysons Rail." I continue to believe that detouring the heavy rail line through Tysons was a mistake, considering that a dedicated-right-of-way circulator system is still needed to service the entire 1700 acres that encompasses the Tysons Corner Urban Center.
Detouring through Tysons was designed to guarantee top dollar real estate values for a few politically well-connected landowners like West*Group and SAIC whose property abuts the proposed stations. And phase I was designed to go to Wiehle Avenue so that toll road money could be used to finance the Commonwealth's portion of the costs.
It appears to me that if Bush wants to stimulate the economy in a sensible and productive way, the federal government would engage in massive expenditures on America's infrastructure, including this project and, for example, repair of highways and bridges, rather as FDR did during the Great Depression. Look how many jobs could be generated, how many small businesses as well as Big Boys would make a profit. We might even restore some of America's lost factories. That's the sort of trickle down that might work (rather than tax cuts for global corporations).
*Significant Cost Increase: States that project costs have increased significantly ($1.5 to $2.7 billion) and project completion has been delayed significantly (4 years) in the last 2 years implying that budget and schedule are already out of control (and the project has not even really started).* No Competition: Points to the "timing of the contract award" and "no competition" on the contract as primary factors for the significant cost increases and delays.
* No Fixed-Price: Points to the fact that there is no comprehensive fixed-price contract for the project.
* Questionable Cost-Effectiveness: Notes that the project had a hard time meeting FTA cost effectiveness standards last year when the project cost was $2.065 billion and may have an even harder time now that the project cost is $2.7 billion.
* FTA Reevaluation: Recommends that the project be evaluated consistent with current FTA policy - in particular, excluding "user benefits" previously counted (possibly making it even harder to meet FTA standards).
* Review Must Be on Merits: Rejects the rationale (of some) that the considerable expenditures to date on the project should weigh as a factor in making decisions on future funding awards - i.e. just because so much money has been spent on the current approach does not mean that more must be spent on that approach . . . the big dollars are still ahead.
* Big Dig: Likens the project to the "Big Dig" and even names Bechtel as a party involved in those troubles, raising collateral questions about MWAA's management capacity for the project.
* Funding Concerns: Notes the heavy reliance on Dulles Toll Road revenues and questions the project financial plan, especially the ability of the Toll Road revenues to support the project costs and maintain the road.
* Tunnel Feasibility: Notes that the ASCE panel reported that the large bore tunnel under Tysons was "feasible and potentially cost-effective" and notes "strong pressure from the public, local government officials, and citizens groups to build a tunnel."
However, the Wilson Bridge's last piece of funding came via an earmark secured by Chuck Robb.
Our elected federal representatives could push for an earmark on this project if they chose. $800M is not a huge earmark in the federal world.
Sen. Ted Stevens can get a bridge to nowhere. I'm not clear why this option isn't being discussed.
Something is very fishy here.
If this no-bid/no cap project goes through and the cost overruns, as predicted by the FTA, do/will occur, all of our legislators should be flogged. This is not good public policy. We have a contractor with a known history of milking mega projects - Bechtal (Boston Dig and Yucca Mountain). No one is watching out for the taxpayers of Fairfax, save the FTA and Foust.
From all appearances, SAIC is paying consultants/employees to make sure that this project goes forward - i.e., Connolly, Clark Tyler, John Mason, NVTA chair, and Planning Commissioner Walter Alcorn. SAIC has a history of partnerships with Bechtal. SAIC management would be "negligent" if they weren't secretly negotiating with Bechtal on the construction portion of the contract - $2.7B and climbing. They have lots of money to throw around - aka Dominion Power style. The lure of candy is just to strong for all our sugar loving legislators.
The rail will most likely go through Gerry C. wants it so that means the NOVA delegation wants it. Big time land owner West*Group now after realizing the tunnel isn't going to happen has switched their point of view and now wants it. So it seems inevitable that the metro will be built.
With that said lets hope the developers stick to the proposed Transit Oriented Development plans, and some good comes from this debacle.